Re-tubing LP EVA, LP ECO & HP ECO HRSG at 50 MW design existing by Sumitomo Corp. and maker by Austrian Energy 3 Unit
May 2012
Material used
- Fin Tube
- Bend Tube
- Connection Piece
- Header Tube
- Suspensions for modules
- Insulation plate board with thermal blanket
Construction Work
- Replacing old tubes with installing new tubes
- Preservation work for HRSG
- Chemical cleaning and passivation
- Blow off
- Site cleaning and management of waste
- Employing Certificated 6G Welder
- Following standard WPS Procedure
- Using Modular Installation Method
Tests and Inspections
- Penetrant test join to header
- 100% X-ray test tube joint
- Hydrostatic test